Initial noticeWithin 45 days
The landlord must advise the tenant that qualifying contractor damage exists.
Additional period15 days
For the itemization and repair cost after the qualifying notice.
Do not treat this as a universal 60-day rule
The additional period is tied to the statute’s specific contractor-damage conditions. A routine deposit accounting does not automatically receive 60 days.
Timeline detail: the normal 45-day rule and the narrow contractor extension are separate. Do not assume every Virginia landlord automatically has 60 days.